September 16, 2004

Phase III starting

Was informed yesterday that the north part of Phase III will be having the desks and partitions placed a week from tomorrow. A week later the rest of the area is to be completed. I requested that the night crew leave the floor open so that I could re-arrange my cables. They did so.

THis is what a raised floor system looks like with half the floor removed. Each of those square black tiles are steel encased concrete -- two feet by two feet. The Electricians have placed the in-floor outlet boxes where each cubicle is to be. Now I get to re-arrange my 25 pair KTS telephone cables and the red & blue Cat-5 cables so that I have a full set in each outlet box.

Posted by at September 16, 2004 08:33 AM
Comments

piece of cake, I could do that :o